IMP 库存优化:给采购与排产装一个"决策大脑" IMP Inventory Optimization: A Decision Brain for Purchasing & Planning
内部分享 · 排产 & 采购部 · 跨月推进中 Internal Share · Planning & Procurement · Ongoing
不替换现有的 NetSuite 和 Cantor,而是在它们之上加一层 "决策智能层":把分散在两个系统里的需求、库存、在途采购、真实交期拼到一起,每天自动算出"什么料、大概什么时候、该下单还是该催货还是该空运",把判断结果只推给排产和采购。
It doesn't replace NetSuite or Cantor — it adds a decision-intelligence layer on top. It stitches together demand, inventory, in-transit purchasing, and real lead times that were scattered across two systems, and each day it works out which material is heading for a shortage, roughly when, and whether to reorder, expedite, or air-freight — routing those calls only to planning and procurement.
1. 我们遇到了什么问题The Problem We Were Sitting On
门窗生产高度依赖进口铝型材和配套材料。这些材料的真实采购周期比系统里设定的补货触发点长得多——也就是说,等系统提示"该补货"时,其实早就晚了。叠加单一来源、供应商质量波动、个别配件供应链特别长等情况,缺料停产、客户交期被迫推迟成了反复发生的痛点。
Our production depends heavily on imported aluminum profiles and related materials. Their real procurement cycle is far longer than the reorder trigger configured in the system assumed — so by the time the system said "reorder," it was already too late. Combined with single-source supply, supplier quality swings, and a few components with especially long supply chains, material shortages and slipped customer dates became a recurring pain.
⚠️ 以前Before
- 需求在 Cantor、采购与库存在 NetSuite,两边对不上
- Demand lived in Cantor, purchasing & inventory in NetSuite — never lined up
- 补货触发点远短于真实交期 → 系统性偏晚
- Reorder trigger far shorter than real lead time → systematically late
- 缺料靠经验和救火,等发现往往来不及
- Shortages caught by gut feel and firefighting — usually too late
- 两个仓库的库存要人工拼,容易误判"有货/没货"
- Stock across two warehouses pieced together by hand — easy to misjudge
- 缺料停产 + 客户交期被迫推迟
- Stoppages from shortages + slipped customer dates
✅ 现在Now
- 两个系统的数据每天自动拼到一张图上
- Both systems' data auto-stitched into one picture daily
- 提前算出"哪天会断料",留出下单/催货时间
- Forecasts the day each material runs short, with lead time to act
- 自动给出建议动作:下单 / 催货 / 空运
- Suggests the action automatically: reorder / expedite / air-freight
- 合并两仓库存,消除"假缺料 / 假有货"
- Merges both warehouses, killing false shortages / false stock
- 从"事后救火" → "提前预警"
- From firefighting → early warning
2. 我们搭了一套什么系统What We Built
核心思路是"不动现有系统、只加一层判断"。Cantor 继续负责销售订单、工单、产能和交期;NetSuite 继续负责采购、收货、库存。新增的智能层只做一件事:把这些数据读过来,按业务逻辑算出材料风险,再把结论交给人去决策。整个判断拆成 5 层逻辑:
The core idea is "don't touch the existing systems — just add a layer of judgment." Cantor still owns sales orders, work orders, capacity, and delivery dates; NetSuite still owns purchasing, receiving, and inventory. The new layer does just one thing: read that data, reason about material risk by business rules, and hand the conclusion to a human to decide. The reasoning is broken into five logical layers:
需求Demand
从已签订单、排产计划和报价推算未来要用掉多少材料。
Derives how much material upcoming orders, the production plan, and quotes will consume.
供应Supply
合并多个仓库的真实库存 + 在途采购,得到"手上加在路上"的总量。
Merges real on-hand stock across warehouses with in-transit purchasing for a true "on-hand + inbound" total.
净缺口Net Gap
需求减供应,沿时间轴画出每种材料的"净位置曲线",看它哪天跌破零。
Demand minus supply, plotted as a net-position curve over time to see the day each material dips below zero.
真实交期Real Lead Time
不按单个料号、而是按"采购路径"把材料分桶,用每桶的实际历史交期,而不是理论值。
Groups materials into buckets by procurement path (not per part number), using each bucket's actual historical lead time rather than a theoretical one.
跟单Follow-Up
跟踪每张采购订单的全生命周期,卡在某个阶段太久就自动报警。
Tracks each purchase order through its full lifecycle and flags any that stalls too long at a stage.
3. 每天早上自动跑一遍It Runs Itself Every Morning
整套流程设成每个工作日早上自动刷新:从两个系统拉最新数据 → 合并库存 → 算净位置 → 生成预警 → 更新看板。团队上班打开看板就是最新结果,没人需要手动操作。
The whole pipeline is set to auto-refresh every workday morning: pull the latest data from both systems → merge inventory → compute net position → generate alerts → update the dashboard. The team opens the dashboard to fresh results — no one has to run anything by hand.
用系统的定时任务每天定点触发,错过了也会自动补跑。需要立刻看最新数据时,也可以手动一键刷新。A scheduled task fires it at a set time each day and catches up automatically if a run is missed. Anyone who needs fresh numbers right away can also trigger a one-click refresh.
4. 一个看板,六个视角One Dashboard, Six Views
所有结果汇总在一个看板里,按标签切换。下面是每个视角"回答什么问题"——不涉及任何具体数字。
Everything lands in one dashboard, switchable by tab. Here's the question each view answers — no specific figures involved.
🚨 缺料预警Shortage Alerts
哪些材料正走向短缺、大概哪天断、该采取什么动作。点开某一行能展开它的未来走势曲线。
Which materials are heading for a shortage, roughly when, and what to do. Click a row to expand its forward trajectory curve.
📉 净位置Net Position
每种铝材未来一段时间的"手上+在途 减 需求"曲线,采购到货当天会出现一个台阶式跳变。支持按系列、窗型筛选搜索。
A forward curve of "on-hand + inbound minus demand" for each profile, with a step jump on the day a PO arrives. Filterable and searchable by series and window type.
♻️ 损耗率Loss Rate
实际用量与理论用量的对比,帮助发现哪些环节损耗偏高、值得追查。
Actual versus theoretical consumption, surfacing where loss runs high and is worth investigating.
🎯 报价胜率Win Rate
从客户、产品系列、销售等多个视角看报价转化情况,给需求预测提供参考。数据不足时会显式标注,绝不静默猜测。
Quote-to-order conversion seen by customer, product series, and salesperson — feeding demand forecasting. When data is thin it says so explicitly, never silently guessing.
📐 备料长度建议Stock Length
基于历史切料情况,建议每种型材按哪个长度备货最省料,并给出操作上可行的方案。
Based on historical cutting patterns, recommends the most material-efficient stock length per profile — and one that's practical on the floor.
📦 采购跟单PO Tracking
把每张采购订单的状态、装柜分配和催货优先级集中展示,让采购知道"先催哪一单"。
Centralizes each PO's status, container allocation, and expedite priority so purchasing knows which order to chase first.
5. 几个关键的思路A Few Key Ideas
这个项目真正的价值不在"代码",而在把业务里的隐性经验变成可计算的规则。几个例子:
The real value isn't the code — it's turning tacit business know-how into computable rules. A few examples:
几千个料号一个个估交期不现实。改成按"采购方式"把材料归成几类,每类用它自己的真实历史交期,既准又好维护。Estimating lead time for thousands of part numbers one by one isn't realistic. Instead, materials are grouped into a handful of buckets by how they're procured, each using its own real historical lead time — more accurate and far easier to maintain.
老的补货点是个固定值,且远短于材料真正到货所需的时间——这正是系统性缺料的根因。新方法让补货点跟随每桶的真实交期和波动自动调整,体现"不缺料优先"。The old reorder point was a fixed value, and far shorter than how long materials actually take to arrive — the root cause of systematic shortages. The new approach lets it adjust to each bucket's real lead time and variability, reflecting a "don't run out" priority.
材料分散在批发仓和工厂仓。系统把两边合并,并按入库、盘点、日常消耗三种事件自动调整,避免"这边显示没货、那边其实有货"导致的误判空运。Material sits in both a wholesale and a factory warehouse. The system merges them and auto-adjusts for three kinds of events — inbound, physical count, and daily consumption — avoiding the false "air-freight now" calls that come from one side showing empty while the other has stock.
采购同事手里的在途订单和跟单记录被整理成统一清单,每个未发货项目按"还能撑多久"自动分高/中/低优先级,采购可以直接拿去跟供应商说"先做这几单"。Purchasing's in-transit orders and follow-up records are pulled into one list, where each unshipped item is auto-ranked high / medium / low by how long stock will last — so purchasing can tell the supplier exactly which to make first.
数据缺失时绝不偷偷用默认值,而是显式标出"这里没数据"并单独列出来。错误的结论比"暂时没有结论"危险得多——宁可空着,也不蒙混。When data is missing, the system never quietly substitutes a default — it explicitly flags "no data here" and lists it out. A wrong conclusion is far more dangerous than "no conclusion yet" — better blank than bluffed.
6. 他们是怎么"不写代码"做出来的How They Built It Without Coding
和我们其它案例一样:业务的人讲清楚规则,Claude 写引擎、调试、改需求。下面是真实迭代过程的缩影。
Like our other cases: the business owners explain the rules, and Claude writes the engine, debugs, and revises. Here's a condensed look at the real back-and-forth.
7. 先"陪跑",再信任Shadow First, Trust Later
👥 只给排产和采购Planning & Procurement only
材料告警只推给排产和采购两个角色,不直接进销售环节——避免半成熟的判断影响对客户的承诺。
Material alerts go only to planning and procurement, never straight into sales — so half-baked judgments don't shape customer commitments.
🌓 影子模式验证Shadow-mode validation
新算法先和现有流程"并行陪跑"一段时间,持续比对准确度,达标后再考虑让它正式参与决策。
New logic runs in parallel with the existing process for a while, accuracy compared continuously, before it's trusted to formally inform decisions.
🗂️ 数据分级Data classification
项目严格区分可共享数据与敏感数据(单价、库存金额、供应商报价等),敏感信息只在受限范围内流转。
The project strictly separates shareable data from sensitive data (unit prices, inventory value, supplier quotes, etc.); sensitive items stay within a restricted circle.
🧩 分清谁是源头Clear source of truth
需求看 Cantor、采购库存看 NetSuite,同一份数据只认一个"源头系统",避免两边打架。
Demand from Cantor, purchasing & inventory from NetSuite — each dataset has exactly one system of record, so the two never contradict.
8. 这个案例告诉我们什么What This Case Shows
经验可以变成规则Tacit → Rules
老师傅"凭感觉"的判断,讲清楚后就能变成每天自动跑的逻辑
A veteran's gut call, once explained, becomes logic that runs every day
打通数据孤岛Bridge silos
不替换系统,用 AI 在两个系统之上做"翻译"和综合判断
Don't replace systems — let AI translate and reason across them
从救火到预警Firefight → Forecast
把"事后才发现"变成"提前几周就知道",留出行动时间
Turn "found out too late" into "known weeks ahead," with time to act
业务人主导Business-led
排产和采购的人自己主导,IT 提供数据接口配合
Planning and procurement lead it; IT supports with data access
谨慎上线Cautious rollout
先陪跑验证、只给相关角色、敏感数据分级——稳扎稳打
Shadow first, scoped audience, classified data — step by step
从小处滚起来Start small
先做一个最痛的点,跑通了再一块块往外扩
Solve the most painful piece first, then expand one block at a time
🌱 最懂业务的人 + AI = 最强组合🌱 The People Who Know the Business + AI = the Strongest Team
这个项目最关键的不是技术,而是排产和采购的同事最清楚"哪里痛、规则是什么"。你不需要会写代码——只要把业务讲清楚,AI 就能把它变成每天帮你干活的工具。从你手上最头疼的那件事开始。The key to this project wasn't the technology — it was that the planning and procurement team knew exactly where it hurt and what the rules were. You don't need to code: explain the business clearly, and AI turns it into a tool that works for you every day. Start with whatever frustrates you most.